MATTER OF FRANCO BELLI PLUMBING & HEATING & SONS, INC. v. NEW YORK CITY SCHOOL CONSTR. AUTH.

2014-07351, Index No. 14334/12.

142 A.D.3d 1011 (2016)

38 N.Y.S.3d 30

In the Matter of FRANCO BELLI PLUMBING AND HEATING AND SONS, INC., Appellant, v. NEW YORK CITY SCHOOL CONSTRUCTION AUTHORITY, Respondent.

Appellate Division of the Supreme Court of New York, Second Department.

Decided September 14, 2016.


Ordered that the order is affirmed, with costs.

We agree with the Supreme Court's determination denying that branch of the petitioner's motion which was for leave to renew its petition pursuant to CPLR 2221 (e), albeit on grounds different from those the court relied upon. In a judgment dated December 21, 2012, the court denied the petitioner's petition seeking to annul a particular determination of the New York City School Construction Authority and dismissed the...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases