FERRANTE IMMOBILIARE, LLC v. PACE

5311, 5311A, 5311B, 108089/06

68 A.D.3d 463 (2009)

2009 NY Slip Op 9059

891 N.Y.S.2d 27

FERRANTE IMMOBILIARE, LLC, et al., Appellants-Respondents, v. GUIDO A. PACE et al., Defendants. GUIDO A. PACE et al., Third-Party Plaintiff, v. VANGUARD CONSTRUCTION AND DEVELOPMENT CO., INC., Third-Party Defendant-Respondent-Appellant.

Appellate Division of the Supreme Court of New York, First Department.

Decided December 8, 2009.


Plaintiffs argue that because Vanguard never substantially completed its work under the contract, the statute of limitations never commenced to run, and that the March 30, 2005 settlement agreement does not necessarily mark the accrual date of their negligence and breach of contract claims since neither a certificate of substantial performance nor a final certificate for payment has ever been issued by the architect Pace as required by the original contract. These arguments...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases