OPINION
FARNAN, District Judge.
Pending before the Court is ALSTOM Power Inc.'s Motion For Partial Summary Judgment (D.I.91). For the reasons discussed, the Motion will be denied.
The claims in this case result from the construction of a 454-megawatt coal-fired power plant built in Guayama, Puerto Rico. In April 1996, AES Puerto Rico, L.P. ("AES") entered into a contract with Duke/Fluor Daniel Carribean...