Ordered that the order is affirmed, with costs.
Contrary to the defendants' contentions, the plaintiff's commencement of this action, inter alia, to foreclose a mechanic's lien in response to the defendants' demand pursuant to Lien Law § 59 did not constitute a waiver of its contractual right to resolve the dispute in arbitration (see, Matter of D.M.C. Constr. Corp., v Nash Steel Corp.,