Ordered that the judgment is affirmed insofar as appealed from, with costs.
Contrary to the petitioner's contention, the Supreme Court correctly determined that respondent Village of Spring Valley had a rational basis for refusing to waive the petitioner's non-compliance with the bid specifications, rejecting its bid on the subject contract, and awarding the contract to the respondent Vitiello Construction, Inc. Therefore, the petition was properly denied and the...