Ordered that the order is modified, on the law, by (1) deleting the provision thereof granting that branch of the cross motion of the defendant Premier-New York, Inc., which was for summary judgment on its cross claim for breach of contract against the defendant McConville Construction Corp. based on its failure to name Premier-New York, Inc., as an additional insured, and substituting therefor a provision denying that branch of the cross motion, and (2) deleting the provision...