EDPL 401 (B) provides an initial limitation period of three years in which a condemnor may commence proceedings to acquire condemned property, with a ten-year limit applicable to projects planned to progress in stages (EDPL 401 [C]). The statute further provides that, on expiration of the three-year period, "the project shall be deemed abandoned, and thereafter, before commencing proceedings under this article the condemnor must again comply with the provisions of [EDPL]...