BEASLEY, Chief Judge.
Southern appeals from the grant of Zartic's motion for summary judgment in this breach of contract case. The trial court determined that suit was filed after the time limitation in OCGA § 11-2-725 had passed.
Southern quoted a price of $77,000 to supply Zartic with a chemical mixing tank and an associated pump and sump. Southern would install it but excavation, foundation, and electrical work would be supplied by other contractors...