BANKE, Presiding Judge.
The appellants contracted with the appellee for the construction of a building. A dispute later arose between the parties, which was submitted to arbitration in accordance with the terms of the contract. Ten days after the initial arbitration hearing, the appellee requested that the arbitrator reopen the hearing pursuant to the "Construction Industry Arbitration Rules" in order to conduct an on-site inspection of the facility. The inspection...