CLYNE, J.S.C.
The question before the court is whether a county utilities authority must obtain local planning board approval before constructing a sludge management facility. During the pendency of the matter, it came to the attention of the court that contractors' bids were about to expire. Counsel therefore agreed to have the court render its decision in an expedited, abbreviated form. That decision was spread upon the record May 8, 1987. It was further understood...