VAN HOOMISSEN, Judge.
Plaintiff appeals from a judgment in her favor arising out of her action for breach of contract. The issue is whether the trial court applied the correct measure of damages. Plaintiff contends that the court erred in fixing damages by using the difference-in-value rule rather than the cost-of-repair rule.
Plaintiff and defendant entered into written contracts whereby defendant agreed to re-roof a house and garage. In her complaint, plaintiff...