The opinion of the court was delivered by MORTON I. GREENBERG, J.A.D.
Plaintiff brought this action against defendant alleging that defendant had breached a contract by not making progress payments when due on a subcontract for structural work being performed by plaintiff for defendant. The prime contract was for the expansion of the Elizabeth postoffice. Defendant was the prime contractor. Defendant counterclaimed for breach of contract, asserting that plaintiff...