[As amended by order of the Court of Appeals May 18, 1977.]
CALLOW, J.
This case concerns the interpretation of a public works contract. It involves a claim for damages by the contractor for delays claimed to have been caused by the municipal corporation. Dyad Construction, Inc. (hereinafter called the contractor), appeals from a judgment entered denying its counterclaim for recovery of delay damages in an action initiated by the municipality, the City of...