OPINION
BOYLE, District Judge:
The plaintiff sues for recovery of a stipulated amount of damages ($21,276.01) representing the cost of repairs to a gantry crane, located at its bulk terminal facility on the Mississippi River Gulf Outlet in the Port of New Orleans, made necessary by collision of a boom of the M/V AGELOS MICHAEL with the crane during docking of the vessel on the morning of May 16, 1973.
The plaintiff contends that this situation calls...