OPINION BY JUDGE ROGERS, January 9, 1973:
Alger-Rau & Associates, Inc., the general contractor of a building for the Commonwealth, has appealed from a decision of the Board of Arbitration and Claims dismissing its claim for expenses occasioned by delay of the work. The delay was caused by the failure of the subsoil at the site to support specified load tests, ultimately cured by the installation of additional footings.
The Commonwealth has moved to quash...