MEMORANDUM AND ORDER
TROUTMAN, District Judge.
On January 29, 1968, Fraim Construction Company entered into a contract with defendant school authority for the construction of a new junior high school in Bangor, Pennsylvania, for the sum of $2,058,839.68. On or about the same date, plaintiff [U.S.F.&G.], as surety, and Fraim, as principal, executed and delivered performance and labor and material payment bonds in connection with the construction project...