This is an action by the United States to enforce a Miller Act performance bond against the defendant surety on a construction contract for modification of a spillway of the Granby Dam in Colorado, upon the default by the contractor and the completion of work by the Government at an excess replacement cost of $76,261.92. The defendant claims in two separate defenses that it is entitled to a set-off of $78,199...