CARR, C.J.
Under date of August 17, 1955, plaintiff entered into a written agreement with defendants Berliner whereby he undertook to construct for them a residence in accordance with specifications and drawings prepared for the work. The total consideration for the contract was the sum of $32,000. During the work of construction or shortly thereafter he was paid the amount specified with the exception of the sum of $1,500, payment of which defendants Berliner refused...