CHAPPELL, Justice.
On September 6, 1949, Burt County Public Power District, hereinafter called defendant, filed a petition with the county judge of Burt County seeking to condemn an easement and right-of-way for the construction and maintenance of a 34,000-volt electric transmission line extending 1 mile on and along the north border of described lands owned by Virgil Lane and Lauren Lane, hereinafter called plaintiffs. On the same date an order providing for appraisal...