(After stating the foregoing facts.) 1-4. Headnotes 1, 2, 3, and 4 require no elaboration.
5. The defendant, by its answer and cross-action, admitted the execution of the contract, and that the housing project had been completed, but denied liability to the plaintiff, and alleged that, because of the negligent performance of its services by the plaintiff, the defendant had incurred additional construction costs in a sum greatly in excess...