LITTLETON, Judge.
Plaintiff seeks to recover $24,400, which it alleges was wrongfully and illegally assessed against it by the defendant as liquidated damages for its alleged delay in completing various portions of work within certain interim periods specified under a contract, whereby the plaintiff company constructed the piers and abutments for the Pit River Bridge in northern California, at the site of the Shasta Dam.
The erection of this bridge was part...