WHITAKER, Judge.
Plaintiff sues for extra costs incurred by reason of delays on the part of the Navy Department of the United States in furnishing it with certain information which it had to have before it could ship ten barges ordered by the Navy.
In August 1944 plaintiff had entered into a contract with the United States Army Transportation Corps to construct for it 11 crane barges. After the cessation of hostilities in Europe this contract was terminated...