HOWELL, Judge.
The plaintiff entered into a cost-plus-a-fixed-fee contract executed March 2, 1944, with the defendant for the construction of the Clinton Engineer Works in Roane County, Tennessee.
Under the terms of the contract the plaintiff was required to procure all necessary permits and licenses and abide by "all applicable laws * * * of the State, Territory, or political subdivision thereof wherein the work is done * * *."
The laws of Tennessee...