KIRKPATRICK, District Judge.
The plaintiff was general contractor for a housing project in Baltimore and one, Shipp, was subcontractor for the preliminary demolition work. The plaintiff's contract with Shipp required the latter to furnish a completion bond. Shipp executed such a bond and the defendant executed it as surety. It was sent to the plaintiff but the plaintiff returned it to the defendant pointing out some minor and immaterial errors and, in addition, requesting...