JONES, Chief Justice.
This is a suit for the recovery of a portion of the liquidated damages assessed against the plaintiff for delay in delivery of articles covered by the contract.
The plaintiff agreed to furnish and deliver to the defendant 600,000 pairs of canvas leggings for the price of $0.725 per pair, in accordance with specifications.
A contract was signed September 17, 1941. Ten percent of the articles were to be delivered within 120 days...