The plaintiff, after nearly a year's delay, finally completed its contract with the government to furnish equipment and machinery for handling boats and seaplanes, for four cruisers. The price was $104,593. From its payments, the government withheld 10% or $10,459.30, as damages for delay in delivery, under a clause of the contract which liquidated the damages at 1/10 of one per cent. of the price for each day's delay, with a limit of 100 days. The plaintiff waived $459.30...